Limited Access to Sailing Club
As part of the HVDC cable laying exercise which is taking place, works will be carried out near to the Sailing Club. Specifically there will be work to undertake route proving under the railway bridge between Monday 27th July and Friday 7th August.
The contractors will maintain access as best as they can during the period. They will be able to maintain foot and emergency access, and in the evening the road surface will be plated.
Please bear this in mind for any planned usage of the club over the next couple of weeks.